Real progress is being made every day at the work site. Please feel free to come and visit the observation room.
| Task Name | Duration | Start | Finish |
| MOB | 2 Days | 6/29/09 | 6/30/09 |
| Blasting & Site Work | 30 Days | 6/15/09 | 7/18/09 |
| Abatement | 14 Days | 6/17/09 | 7/2/09 |
| Demo of Simpler House | 5 Days | 6/29/09 | 7/3/09 |
| Form & Pour Footings | 8 Days | 7/20/09 | 7/28/09 |
| Form & Pour Walls | 34 Days | 7/29/09 | 9/5/09 |
| Form & Pour Slab | 7 Days | 9/7/09 | 9/14/09 |
| Set Steel | 24 Days | 9/7/09 | 10/3/09 |
| Pour Roof Slab | 7 Days | 10/5/09 | 10/12/09 |
| Install Roof | 24 Days | 10/12/09 | 11/9/09 |
| Frame & Sheet | 8 Days | 10/5/09 | 10/13/09 |
| Install Siding | 7 Days | 10/10/09 | 10/17/09 |
| Interior Framing | 14 Days | 10/12/09 | 10/27/09 |
| Mechanical | 180 Days | 10/12/09 | 5/11/10 |
| Electrical | 180 Days | 10/12/09 | 5/11/10 |
| Sheetrock | 20 Days | 11/2/09 | 11/26/09 |
| Finishes | 150 Days | 11/23/09 | 5/17/10 |
| Substantial Completion | 1 Day ? | 7/15/10 | 7/16/10 |

No Comments so far ↓
There are no comments yet...Kick things off by filling out the form below.