Simpler Gym Construction Time Line

Real progress is being made every day at the work site. Please feel free to come and visit the observation room.

Task Name Duration Start Finish
MOB 2 Days 6/29/09 6/30/09
Blasting & Site Work 30 Days 6/15/09 7/18/09
Abatement 14 Days 6/17/09 7/2/09
Demo of Simpler House 5 Days 6/29/09 7/3/09
Form & Pour Footings 8 Days 7/20/09 7/28/09
Form & Pour Walls 34 Days 7/29/09 9/5/09
Form & Pour Slab 7 Days 9/7/09 9/14/09
Set Steel 24 Days 9/7/09 10/3/09
Pour Roof Slab 7 Days 10/5/09 10/12/09
Install Roof 24 Days 10/12/09 11/9/09
Frame & Sheet 8 Days 10/5/09 10/13/09
Install Siding 7 Days 10/10/09 10/17/09
Interior Framing 14 Days 10/12/09 10/27/09
Mechanical 180 Days 10/12/09 5/11/10
Electrical 180 Days 10/12/09 5/11/10
Sheetrock 20 Days 11/2/09 11/26/09
Finishes 150 Days 11/23/09 5/17/10
Substantial Completion 1 Day ? 7/15/10 7/16/10