Simpler Gym Construction Time Line

July 18th, 2009 · No Comments · Renovation

Real progress is being made every day at the work site. Please feel free to come and visit the observation room.

Task Name Duration Start Finish
MOB 2 Days 6/29/09 6/30/09
Blasting & Site Work 30 Days 6/15/09 7/18/09
Abatement 14 Days 6/17/09 7/2/09
Demo of Simpler House 5 Days 6/29/09 7/3/09
Form & Pour Footings 8 Days 7/20/09 7/28/09
Form & Pour Walls 34 Days 7/29/09 9/5/09
Form & Pour Slab 7 Days 9/7/09 9/14/09
Set Steel 24 Days 9/7/09 10/3/09
Pour Roof Slab 7 Days 10/5/09 10/12/09
Install Roof 24 Days 10/12/09 11/9/09
Frame & Sheet 8 Days 10/5/09 10/13/09
Install Siding 7 Days 10/10/09 10/17/09
Interior Framing 14 Days 10/12/09 10/27/09
Mechanical 180 Days 10/12/09 5/11/10
Electrical 180 Days 10/12/09 5/11/10
Sheetrock 20 Days 11/2/09 11/26/09
Finishes 150 Days 11/23/09 5/17/10
Substantial Completion 1 Day ? 7/15/10 7/16/10

Tags:

No Comments so far ↓

There are no comments yet...Kick things off by filling out the form below.

Leave a Comment

*
To prove you're a person (not a spam script), type the security word shown in the picture.
Anti-Spam Image