Simpler Gym Construction Time Line

July 18th, 2009 · No Comments · Renovation

Real progress is being made every day at the work site. Please feel free to come and visit the observation room. Task Name Duration Start Finish MOB 2 Days 6/29/09 6/30/09 Blasting & Site Work 30 Days 6/15/09 7/18/09 Abatement 14 Days 6/17/09 7/2/09 Demo of Simpler House 5 Days 6/29/09 7/3/09 Form & Pour [...]